2 x 900 MW Nuclear Power Station - Ling Ao, Guangdong - China

Copy and modify an existing PDS Design of a 900 MW Steam Turbine Hall involving the following deliverables:-

  • Clash Reports
  • 1130 no. pipe fabrication isometrics c/w BOM's by system, work unit and individual isometric
  • 1550 no. detailed pipe supports together with intelligent BOM reports by project area, system, and individual support.
  • 132 no. piping/equipment/electrical panel location GA's
  • Updating & maintaining 60 no. P&ID's
  • Photo-realistic views
  • Walk throughs and fly-arounds transferred to CD and video

Project Size

  • 21,000 m of 50ns pipe & below (indicative)
  • 24,000 m of 80ns pipe & above
  • 540 no. separate lines
  • 40 no. piping systems