2 x 600 MW Coal Fired Power Station - Ho Ping - Taiwan

PDS model the “off site” pipe-work and equipment (Site 900m x 300m) including all structures, buildings, roads, drains, coal & ash handling, oil, water, air, steam & gas storage / distribution i.e. all BOP service and process systems, and produce the following design deliverables:-

  • 1250 no. pipe fabrication isometrics c/w BOM's by system, work unit and individual isometric
  • 200 no. detailed special pipe supports together with BOM reports by project area, system, and individual support.
  • 6000 no. standard pipe supports together with BOM reports by project area, system and individual supports
  • 184 no. piping GA's, 45 no. civil location GA's, Updating & maintaining 16 no. P&ID's, 200 no. stress isometrics

Project Size

  • 21,600 m of 50ns pipe & below (indicative)
  • 42,000 m of 80ns pipe & above
  • 703 separate Lines
  • 15 piping systems